Step 1

PRS Bottom Unit is driven into the soil OR placed in an augered hole and well tamped.

Step 2

PRS Upper Unit is placed over the bottom unit and rested on the ground.

Step 3

Bolting: Three pairs of cross bolts are connected to the specially tapered upper unit, structurally connecting the units to the pole.

Step 4

Banding: two high strength galvanized bands are placed near the bottom, eliminating drilling and exposing untreated wood at the ground line.